VSB Group Connects One of Europe's Largest Repowering Projects to the Grid

VSB Group Connects One of Europe's Largest Repowering Projects to the Grid

DRESDEN, Germany, Aug. 15, 2025 -- The VSB Group has successfully connected the Repowering Wind Farm Elster to the grid. With an installed capacity of 105.6 megawatts, it ranks among the largest repowering projects in Europe. The energy output has increased sixfold compared to the original site – made possible by state-of-the-art turbine technology.

More energy, less land use

The new wind farm produces 235 gigawatt hours of electricity per year – enough to supply around 67,000 three-person households, comparable to a city the size of Heidelberg. "Every kilowatt hour from Repowering Wind Farm Elster strengthens Europe's energy sovereignty and brings us closer to achieving the EU's climate targets," says Dr Felix Grolman, CEO of the VSB Group.

Repowering sets new standards

With an efficiency increase of nearly 600 percent, the Elster site demonstrates the vast potential of repowering. This strategy is particularly promising in countries like Germany and France, where many older turbines are still in operation.

Future-proof development of existing sites

VSB has been involved with the Elster location for over two decades. Between autumn 2021 and autumn 2022, the legacy turbines were dismantled. Many of their components were given a second life – either reused for spare parts or in continued operation elsewhere.

"Grid connection, permitting, dismantling – the project posed significant challenges in every phase," points out Thomas Winkler, Managing Director of VSB Germany, which was responsible for planning and construction. "Its successful completion shows how existing sites can be future-proofed through long-standing experience and close cooperation with local partners and authorities."

European technology, measurable benefits

The 16 SG 6.6-155 turbines come from European manufacturer Siemens Gamesa. "Modern turbines like the SG 6.6-155 deliver higher yields using less land – and make a clearly measurable contribution to climate protection," adds Christian Essiger, Head of Onshore Business in Germany at Siemens Gamesa. "Each turbine generates around 48 times more energy over its lifetime than is needed for manufacturing, installation and operation."

Expansion starts this autumn

Two additional turbines will be added in autumn 2025. For Grolman, the path forward is clear: "Fewer turbines, more output, and smart use of available land – that's the key to a strong European wind industry."

Fact box: Old turbines vs. new turbines


Former wind farm (decommissioned turbines)

Repowered wind farm

Number of turbines

50

16

Turbine type

Enercon E-40

Siemens Gamesa
SG 6.6-155

Commissioning

Between 2000 and 2002

2025

Capacity per turbine

0.6 MW

6.6 MW

Total installed capacity

30 MW

105.6 MW

Annual energy yield

36 GWh

235 GWh

Hub height

77.8 metres

165 metres

Rotor blade length

20 metres

77.5 metres

Total height (tip)

97.8 metres

242.5 metres

 
Detailed information as well as image and video material related to the announcement
https://vsb.canto.global/b/VKVK6

This News is brought to you by Qube Mark, your trusted source for the latest updates and insights in marketing technology. Stay tuned for more groundbreaking innovations in the world of technology. 

PR Newswire

PR Newswire empowers communicators to identify and engage with key influencers, craft and distribute meaningful stories, and measure the financial impact of their efforts. Cision is a leading global provider of earned media software and services to public relations and marketing communications professionals.